Civil engineering, permit coordination, and construction administration for the re-development of a 0.73-acre existing commercial site for the construction of a Starbucks coffee house.
This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
Civil engineering, permit coordination, and construction administration for the removal and replacement of an deteriorated parking lot with a 107,500-sf light industrial building.
Isomer provided conceptual site layout, permitting, and conditional use application support for a portfolio of solar, battery storage, and hydrogen facilities across the US.
FEL2 through detail design engineering for a velvet manufacturer facility relocation. Scope of work included a site walk down, equipment and facility studies, 3D modeling (including VR walkthrough), heavy civil coordination, and wetlands study.
This effort included the detailed design, procurement, and construction management for a $80 million brownfield polymer manufacturing facility expansion.
This effort included the detailed design, material procurement, construction planning and construction management for a $3 million brownstock washing system upgrade.
Existing mill conversion from fine paper to linerboard production using 100% OCC furnish including new OCC facility and warehouse, conversion of existing machine, conversion of two boilers, and other utility upgrades.
This effort included the detailed design and procurement support for a $400 million brownfield through-air-drying (TAD) tissue machine installation and supporting infrastructure. The facility design included all processes necessary...
Detailed design including site development, foundations, electrical, and mechanical design for a 40,000SF maintenance warehouse built to service steel processing equipment