This project included detailed design and procurement support for the main polysilicon production building, the largest project on the campus of a multi-billion-dollar greenfield manufacturing site...
This project focused on installation a new 1 million gallon molten sulfur tank in an existing sulfuric acid production facility. The design including supporting piping electrical and structural modifications.
Civil engineering design, permit coordination, and construction administration for the development of a 1.2-acre site for an 3,000-sf Zaxby's quick service restaurant.
Detailed design, procurement, and construction (EPC) services for a $300 million coal-fired power plant regulatory program including fly ash, bottom ash, and water management conversions.
Isomer provided detailed design engineering, permitting, and construction support for a $60 million 50 MW-DC solar facility located on 365-acres in Idaho.
Civil engineering design, permit coordination, and construction administration for the development of a 1.9-acre outparcel for a dental office utilizing a common pond for stormwater detention.
This effort included the detailed design, material procurement, construction planning and construction management for a $3 million brownstock washing system upgrade.
Detailed design engineering for a 10-foot diameter downcomer duct replacement project in an existing 250-foot tall preheater tower, including significant structural reinforcements.
This effort included detailed engineering on a four project Anaerobic Digestion to biogas program with site locations in Georgia and California. The facilities were located on existing dairy farms of approximately 12,000 cows each...