The project included front-end engineering and detailed design for a multi-year facility expansion at a honeycomb scrubber plant to facilitate a six-fold increase in production capacity.
Project management and construction oversight for an $8 million chemical manufacturing facility upgrade, including direct supervision of detailed design and construction bid process.
This effort included the completion of the conceptual design (FEL2) phase for a $5 million USD water sustainability program for an existing Fiber Optics facility with a goal to reduce water consumption at the site by 80%.
Detailed design engineering to support the relocation of an existing 6,000-gallon clarifier and 2,000-gallon aeration tank into a new multi-story building extension at an operating sugar mill.
FEL-3 Engineering for the ISBL area of a 12,000 TPA proprietary electrolyte production facility, including all process, piping, and instrumentation & controls design.
Capital cost estimating and detailed design engineering for a $5MM TIC project to upgrade dry end handling capabilities at an existing chemicals facility.
Full-service conceptual design FEL2 services for the infrastructure project to support the Lithium Battery-grade 47ktpa Refrigerant and 10ktpa Electrolyte Facility Expansion projects at an existing chemicals plant in the southeast.
Conceptual engineering evaluating alternatives for a new finished product tank farm, replacing one large field-erected tank with shop-fabricated tanks and assessing enclosure options to minimize operational disruption.
Comprehensive site logistics study to evaluate and improve inbound and outbound truck routing for a cement manufacturing facility to relieve heavy onsite traffic congestion.
FEL1 study for a 6 ktpa battery-grade phosphoric acid plant co-located with 10 ktpa sulfuric acid facility, including process validation and several alternatives analyses.