Front-end engineering and project development services to determine feasibility and conceptual layout for 400 MW-DC solar facility with 200-MW BESS located in Nebraska.
Technical due diligence for a financier on a Waste Heat to Power asset in construction to support financial close, as well as an evaluation of the company's development pipeline.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
This project included a contract for detailed design following a transition from another engineering firm at less than 10% complete; however, construction activities had already begun in the field. The scope of the project...
FEL1 preliminary engineering design for a first-of-a-kind 1KTPA facility to produce Cathode Active Materials for EV batteries, including scale-up from an existing lab-scale processes.
Preliminary cost modeling in support of a developer with novel turbine technology intended to be retrofitted or incorporated into chillers for data centers to increase performance.
Isomer provided conceptual site layout, permitting, and conditional use application support for a portfolio of solar, battery storage, and hydrogen facilities across the US.
Front-end engineering and project development services to determine feasibility and order of magnitude costs for a greenfield facility with 150MW Electrolyzers and balance of plant infrastructure.
Civil engineering design and development to support for the conceptual (30%) design of a 75 MW-DC solar facility located on 330-acres in Nevada located within heavy floodplains.