FEL2 Engineering and Owner’s Engineering Services for a 180 TPD Tissue Machine Yankee Dryer Hood Replacement project as part of a Fleet-wide Rebuild Program.
This effort included the detailed design and procurement support for a $250 million brownfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary to produce premium quality parent rolls..
Comprehensive site logistics study to evaluate and improve inbound and outbound truck routing for a cement manufacturing facility to relieve heavy onsite traffic congestion.
Detailed design and engineering services for a $45 million containerboard machine rebuild project at an existing facility featuring a new shoe press and an iTable to replace the existing top-wire former.
This effort included the detailed design, procurement, and construction management for a $80 million brownfield polymer manufacturing facility expansion.
Fluff Pulp Machine Upgrade Project with the objective to increase production of the paper machine through machine and other auxiliary system modifications.
FEL2 and Detailed Design Engineering of ISBL scope for a new Drywall Compound Manufacturing Facility to expand client’s market footprint into a new location and optimize plant performance.
Detailed Design and Construction Oversight of all heavy critical lifts required to construct one of the world’s largest simple cycle gas turbines and its associated components.
Detailed design for a maintenance and reliability project on an existing linerboard machine that included the installation of a new dust collection system to address issues with glue and sensor reliability caused by the presence of excess dust.
Detailed design engineering in a design-build arrangement for a 60,000 SF roll finishing and shipping warehouse install at an existing pulp & paper mill as part of a major modernization effort.