Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
Front-end engineering study for a new low consistency storage tower and pump integrated into an existing 30 TPD ag-based fiber pulping process facility.
Basic engineering phase (FEL-3) for a $5 million project to add silicone-based and water-based defoamers process lines in an existing chemical processing facility.
Civil engineering, permit coordination, and construction administration services for redevelopment of a 0.4-acre existing parking lot to support construction of a four-story office building in downtown Greenville.
This effort included the detailed design and procurement support for a $250 million brownfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary to produce premium quality parent rolls..
Front-end engineering and project development services to determine feasibility and conceptual layout for 210 MW-DC solar facility located in Arizona.
FEL-2 design to support upgrades to an existing linerboard paper machine roll handling line, including conveyors, a lowerator, and shipping floor conveyors for loading finished product rolls into railcars.
Detailed design for a maintenance and reliability project on an existing linerboard machine, including improvements for the existing tail cutter system to reduce damage to felts and improve overall machine runnability.
Preliminary engineering services in support of a thermoforming capacity increase at an existing molded fiber production facility, including a cost-benefit analysis and extensive utility study.
FEED and Detailed Design Engineering for a new tank farm with 300,000 gallons of total capacity to store a combination of Class I, II, and III flammable and combustible liquids.