This effort included the FEL3 and detailed design for a new reactor structure, associated equipment and supporting insfras turecture at an existing surfactant production facility.
Structural detailed design for a clinker cooler retrofit, including steel and concrete modifications to support a new 200HP ID fan and associated ductwork.
This project included detailed design and procurement support for the main polysilicon production building, the largest project on the campus of a multi-billion-dollar greenfield manufacturing site...
Designing temporary construction facilities on a constrained worksite, including a lunch/break tent over an existing ditch line, to support the EPC contractor's construction of new HRSG units at an existing generating station.
FEL2 through detail design engineering for a velvet manufacturer facility relocation. Scope of work included a site walk down, equipment and facility studies, 3D modeling (including VR walkthrough), heavy civil coordination, and wetlands study.
Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
Civil engineering, permit coordination, and construction administration services for redevelopment of a 0.4-acre existing parking lot to support construction of a four-story office building in downtown Greenville.
Isomer provided Technical Due Diligence for a potential investment in a solar development platform, reviewing solar and BESS production targets, technology, EPC execution capabilities, and project economics to identify critical risks and red flags.
The scope consisted of developing a companywide reliability program for a major pulp and paper corporation. The project team led a group that included contractors from three separate companies with extensive reliability programs...