Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
Civil engineering, permit coordination, and construction administration for the development of 365-acres of existing agricultural land for a 50 MW-DC solar facility.
Front-end engineering services and project development support for a new three stage feedstock cleaning/storage system at an existing non-wood ag-based pulping and molding facility.
Detailed design and project management for a $100 million, 2,000 MTPD Semi-Dry Cement Plant upgrade, featuring a new pyroline, at an existing facility in Oklahoma.
FEL2 through detail design engineering for a velvet manufacturer facility relocation. Scope of work included a site walk down, equipment and facility studies, 3D modeling (including VR walkthrough), heavy civil coordination, and wetlands study.
This effort included the detailed design, procurement, and construction management for a $80 million brownfield polymer manufacturing facility expansion.
This effort included the detailed design, material procurement, construction planning and construction management for a $3 million brownstock washing system upgrade.
Existing mill conversion from fine paper to linerboard production using 100% OCC furnish including new OCC facility and warehouse, conversion of existing machine, conversion of two boilers, and other utility upgrades.
This effort included the detailed design and procurement support for a $400 million brownfield through-air-drying (TAD) tissue machine installation and supporting infrastructure. The facility design included all processes necessary...
Detailed design including site development, foundations, electrical, and mechanical design for a 40,000SF maintenance warehouse built to service steel processing equipment