The scope of this effort consisted of front-end engineering for a significant capacity increase for an existing polymer facility. The facility produces high-performance elastomers used as replacements for rubber. The project team...
Front-end engineering and project development services to determine feasibility and order of magnitude costs for a greenfield facility with 150MW Electrolyzers and balance of plant infrastructure.
Front end engineering, detailed design, and Project Management and Construction Oversight services for a $5MM TIC warehouse expansion project at a 25 TPD ag-based pulp thermoforming facility.
Conceptual civil engineering and site plan development to support the preliminary plan approval for a 12,000-square foot indoor pickleball and badminton facility.
Project management and Owner's Engineering in support of an FEL-3 study to convert an existing paper machine from newsprint to liner board and medium grades. The scope included a new OCC plant, new steam turbine, and a full paper machine rebuild.
This effort included the detailed design and construction support to install a River Water Intake System and Raw Water Treatment system to support an Ammonium Nitrate Solution (ANSol) plant in Tennessee.
Isomer provided detailed design for a $6 million battery storage project to enhance grid stability by providing additional capacity during times of peak consumption for the city utility.
This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
This effort included the detailed design and procurement support for a $250 million brownfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary to produce premium quality parent rolls..