Isomer completed project technical and financial due diligence on a series of 19 projects producing renewable natural gas (RNG) from anaerobic digestion to support a private equity firm.
Front end engineering study to evaluate the feasibility of installing pressure screening systems on existing stock approach loops at an ag-based pulp thermoforming facility.
Front-end engineering and project development support for a 450,000 TPA greenfield wood pellet plant. Roundwood and residuals were used for feedstock. Facility included rotary drying, rail and truck loadout capability.
This effort included detailed engineering on a four project Anaerobic Digestion to biogas program with site locations in Georgia and California. The facilities were located on existing dairy farms of approximately 12,000 cows each...
This effort included the detailed design, permitting, and construction support for the balance of plant (BOP) systems on a 1400 BPD facility converting woody biomass into renewable fuels.
FEL2 front-end engineering design to evaluate a deficient vacuum seal water cooling loop at an existing molded fiber facility and replace an undersized cooling tower and supply pumps.
Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
This scope consisted of multiple layers of support for the re-development of a 48 MW biomass-fired power plant that had been moth-balled in the middle of the initial construction process. As the project found new life...
FEL1 and detailed design to double the capacity of an existing ag-pulp feedstock processing line, including modifications to material handling, hammer mill, pneumatic transport, and conveying systems.