Detailed design engineering to support the installation of a new rotary strainer for a milling tandem at an operating sugar mill, including a new steel structure and foundation constructed in a heavy brownfield environment.
Front-end engineering and project development support for a 450,000 TPA greenfield wood pellet plant. Roundwood and residuals were used for feedstock. Facility included rotary drying, rail and truck loadout capability.
Preliminary engineering support of a first-of-its-kind ag-based pulping and thermoforming facility, including heat & material balance development and other key activities.
Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
Multi-discipline front-end engineering and estimating services for a facility using a proprietary process to convert waste cellulose into consumer product replacements.
This effort included the detailed design, permitting, and construction support for the balance of plant (BOP) systems on a 1400 BPD facility converting woody biomass into renewable fuels.
Conceptual engineering to support the evaluation of an existing anaerobic digestion facility to receive additional liquid waste feedstocks for co-digestion.
Owner’s Engineering and support during the pre-FID engineering phase (FEL3) for a new 20 million gallons per year Renewable Fuel Oil Production Facility.
This scope consisted of multiple layers of support for the re-development of a 48 MW biomass-fired power plant that had been moth-balled in the middle of the initial construction process. As the project found new life...