Detailed design for rerouting broke from an existing linerboard machine to the OCC system to improve water balance, remove fines, and increase fiber recovery.
FEL2 front-end engineering design to evaluate a deficient vacuum seal water cooling loop at an existing molded fiber facility and replace an undersized cooling tower and supply pumps.
Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
Front-end engineering services and project development support for a new three stage feedstock cleaning/storage system at an existing non-wood ag-based pulping and molding facility.
Detailed design and FEL2 for a 25 TPD molded fiber production facility. Design included new repulping, stock prep, thermoforming, and utility systems located in an existing manufacturing facility.
Front end engineering, detailed design, and Project Management and Construction Oversight services for a $3MM TIC project to expand an existing vacuum system at a 25 TPD ag-based pulp thermoforming facility.
Project management and Owner's Engineering in support of an FEL-3 study to convert an existing paper machine from newsprint to liner board and medium grades. The scope included a new OCC plant, new steam turbine, and a full paper machine rebuild.
Detailed design, procurement, and construction support for a $300 million brownfield, 100% recycled (OCC) linerboard machine installation to produce premium and back ply liner.
This effort included the FEED package, detailed design, and construction support for restarting an existing Paper Machine and supporting systems and infrastructure at a legacy mill.
Preliminary engineering support of a first-of-its-kind ag-based pulping and thermoforming facility, including heat & material balance development and other key activities.