Technical due diligence on a CO2 capture asset currently under construction, and a broader evaluation of the company's portfolio of development assets for a financing partner.
Isomer completed project technical and financial due diligence on a series of 19 projects producing renewable natural gas (RNG) from anaerobic digestion to support a private equity firm.
FEL1 and detailed design to double the capacity of an existing ag-pulp feedstock processing line, including modifications to material handling, hammer mill, pneumatic transport, and conveying systems.
This scope consisted of a detailed technical review conducted supporting due diligence for a project where landfill gas (LFG) was extracted via an existing system. The extracted LFG was then to-be-processed and converted...
Isomer completed an engineering review of a proposed facility producing lithium carbonate and rare earth oxides from recycled batteries and magnets, assessing technology, scale-up, site, demand, and finances in a report with findings and red flags.
Isomer provided front-end engineering and project development services for a 10 ktpa electrochemical process for H2SO4 production, including alternatives analysis for carbon capture and a supplementary cementitious material co-product.
Performed third-party engineering due diligence to identify major risks and red flags for a project installing a Textile Recycling Facility into an existing mothballed manufacturing facility.
Civil engineering conceptual planning, design, and permit coordination for redevelopment of an existing 0.25-acre residential lot into three (3) single-family homes in downtown Greenville.
FEL1 Engineering and Site Selection services for a 200,000 TPY, First-of-its-Kind, Commercial Scale Facility to manufacture Ultra-low-Carbon Cement, co-located at an existing cement plant.