Existing mill conversion from fine paper to linerboard production using 100% OCC furnish including new OCC facility and warehouse, conversion of existing machine, conversion of two boilers, and other utility upgrades.
This effort included the detailed design and procurement support for a $400 million brownfield through-air-drying (TAD) tissue machine installation and supporting infrastructure. The facility design included all processes necessary...
This effort centered around providing early-stage project development services for a brownfield wood pellet plant rated at 150,000 metric tons per year. Residuals from nearby sawmills made up all of the feedstock used for this project. ..
Isomer provided conceptual site layout, permitting, and conditional use application support for a portfolio of solar, battery storage, and hydrogen facilities across the US.
Front end engineering study to evaluate the feasibility of firing a secondary biomass fuel in three separate biomass boilers at an existing facility in an effort to reduce the consumption of the primary fuel source.
Isomer provided detailed design engineering, permitting, and construction support for a $60 million 50 MW-DC solar facility located on 365-acres in Idaho.
Front end engineering design and technology trials support for a liquor coproduct contaminant reduction system at an existing 30TPD ag-based pulp mill.
Pre-FEL study and FEL1 design of a primarily greenfield 150TPD ag-based pulp molded fiber facility, including feedstock handling and separation, material storage, semi-chem pulping, stock preparation, and molding.
The project included front-end engineering and detailed design for a multi-year facility expansion at a honeycomb scrubber plant to facilitate a six-fold increase in production capacity.
This project effort included detailed design and construction support for a turnkey, full-scale Ethylene Oxide production facility along the Delaware River.