Comprehensive site logistics study to evaluate and improve inbound and outbound truck routing for a cement manufacturing facility to relieve heavy onsite traffic congestion.
Civil engineering design, permit coordination, and construction administration for the development of a 2.0-acre site for a 4,500-sf auto glass repair shop and 10,000-sf flex building.
Conceptual civil engineering and site plan development to support the preliminary plan approval for a 12,000-square foot indoor pickleball and badminton facility.
Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
Project management and construction oversight for an $8 million chemical manufacturing facility upgrade, including direct supervision of detailed design and construction bid process.
Structural feasibility study to evaluate the potential addition of rooftop solar panels to multiple existing structures at a chemicals manufacturing facility, as well as the potential for adding panels over existing stormwater infrastructure.
This scope consisted of front-end engineering and detailed design to increase the bark firing capacity of an existing combination boiler at a paper mill. Initial studies identified issues, and the project team proceeded...
Detailed design and project management for a $100 million, 2,000 MTPD Semi-Dry Cement Plant upgrade, featuring a new pyroline, at an existing facility in Oklahoma.
Front-end engineering and project development services to determine feasibility and conceptual layout for 400 MW-DC solar facility with 200-MW BESS located in Nebraska.
FEL2 through detail design engineering for a velvet manufacturer facility relocation. Scope of work included a site walk down, equipment and facility studies, 3D modeling (including VR walkthrough), heavy civil coordination, and wetlands study.