Detailed design for a maintenance and reliability project on an existing linerboard machine that included the installation of a new dust collection system to address issues with glue and sensor reliability caused by the presence of excess dust.
Detailed design engineering for replacement of an existing 240V MCC with a new 480V MCC at a specialty chemical facility, including relocation and refeed of wall-mounted loads to the new MCC.
This scope consisted of a detailed technical review conducted supporting due diligence for a project where landfill gas (LFG) was extracted via an existing system. The extracted LFG was then to-be-processed and converted...
Isomer completed project technical and financial due diligence on a series of 19 projects producing renewable natural gas (RNG) from anaerobic digestion to support a private equity firm.
This effort included the basic design (FEL1-2) phase for a greenfield $37 million USD Lithium-Ion Battery recycling facility. The owner operates facilities throughout Asia and Europe and this facility is their first in the United States.
Conceptual site planning for a portfolio of parcels to complete test fits of commercial developments, generating concept plans, layouts, and imagery for use in marketing materials.
Detailed design engineering for a 10-foot diameter downcomer duct replacement project in an existing 250-foot tall preheater tower, including significant structural reinforcements.
FEL1 Engineering and Owner’s Engineering Services for a 170 TPD Tissue Machine Dry End Replacement project including the Yankee Dryer, Hood, and Air System, as part of a Fleet-wide Rebuild Program.
FEL3 engineering package for the installation of two new reactors to replace an existing end-of-life reactor vessel at a specialty chemicals facility.
This scope consisted of multiple layers of support for the re-development of a 48 MW biomass-fired power plant that had been moth-balled in the middle of the initial construction process. As the project found new life...