Detailed design for a maintenance and reliability project on an existing linerboard machine that included the installation of a new dust collection system to address issues with glue and sensor reliability caused by the presence of excess dust.
Detailed design engineering for replacement of an existing 240V MCC with a new 480V MCC at a specialty chemical facility, including relocation and refeed of wall-mounted loads to the new MCC.
This scope consisted of a detailed technical review conducted supporting due diligence for a project where landfill gas (LFG) was extracted via an existing system. The extracted LFG was then to-be-processed and converted...
Isomer completed project technical and financial due diligence on a series of 19 projects producing renewable natural gas (RNG) from anaerobic digestion to support a private equity firm.
Comprehensive structural inspection and due diligence reporting for fleet of 15+ production and distribution facilities, working to identify immediate risks to market supply.
This project included a contract for detailed design following a transition from another engineering firm at less than 10% complete; however, construction activities had already begun in the field. The scope of the project...
This project effort included detailed design and construction support for a turnkey, full-scale Ethylene Oxide production facility along the Delaware River.
This effort included the completion of the conceptual design (FEL2) phase for a $5 million USD water sustainability program for an existing Fiber Optics facility with a goal to reduce water consumption at the site by 80%.
This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
Detailed design engineering for a $45MM TIC laser guided vehicle operated distribution center at an existing sugar mill and refinery, including the integration into an existing warehouse and packaging building.