FEL2 preliminary study and detailed design engineering for a new concrete containment area for chemical railcar loading at an existing production facility.
This $150 million scope consisted of conceptual engineering, front-end engineering, and detailed design to meet an issued environmental consent decree at three similar yet unique metallurgical coking facilities...
Front-end engineering and project development services to determine feasibility and order of magnitude costs for a greenfield facility with 150MW Electrolyzers and balance of plant infrastructure.
Preliminary engineering services in support of a thermoforming capacity increase at an existing molded fiber production facility, including a cost-benefit analysis and extensive utility study.
Project management and construction oversight for an $8 million chemical manufacturing facility upgrade, including direct supervision of detailed design and construction bid process.
This scope consisted of a detailed technical review conducted supporting due diligence for a project where landfill gas (LFG) was extracted via an existing system. The extracted LFG was then to-be-processed and converted...
This effort included the FEED package, detailed design, and construction support for restarting an existing Paper Machine and supporting systems and infrastructure at a legacy mill.
This scope consisted of full-cycle project support from front-end engineering through startup for the conversion of an existing power boiler from coal firing to natural gas at an existing paper mill. The project installed six new...
Detailed design engineering and construction oversight for a new oil tank farm, oil conditioning system, utilities, and impregnation system for film capacitors.
Detailed design, procurement, and construction (EPC) services for a $300 million coal-fired power plant regulatory program including fly ash, bottom ash, and water management conversions.