Detailed design including site development, foundations, electrical, and mechanical design for a 40,000SF maintenance warehouse built to service steel processing equipment
Root cause analysis for a significant vibration issue affecting a group of dryer cans on an existing paper machine, including both onsite and offsite analysis.
Capital cost estimating and detailed design engineering for a $5MM TIC project to upgrade dry end handling capabilities at an existing chemicals facility.
Isomer completed project technical and financial due diligence on a series of 19 projects producing renewable natural gas (RNG) from anaerobic digestion to support a private equity firm.
Detailed design engineering for a $45MM TIC laser guided vehicle operated distribution center at an existing sugar mill and refinery, including the integration into an existing warehouse and packaging building.
Detailed design engineering in a design-build arrangement for a 60,000 SF roll finishing and shipping warehouse install at an existing pulp & paper mill as part of a major modernization effort.
This scope consisted of front-end engineering and detailed design to increase the bark firing capacity of an existing combination boiler at a paper mill. Initial studies identified issues, and the project team proceeded...
Independent reviews of several projects ranging from $50-800MM TIC to serve as input prior to final project funding, including visits to project sites to conduct multiday in-person interviews and site walks to supplement desktop review.
This effort included detailed engineering on a four project Anaerobic Digestion to biogas program with site locations in Georgia and California. The facilities were located on existing dairy farms of approximately 12,000 cows each...
Conceptual engineering to support the evaluation of an existing anaerobic digestion facility to receive additional liquid waste feedstocks for co-digestion.