Detailed design and FEL2 for a 25 TPD molded fiber production facility. Design included new repulping, stock prep, thermoforming, and utility systems located in an existing manufacturing facility.
Front-end engineering and project development services to determine feasibility and order of magnitude costs for a greenfield facility with 150MW Electrolyzers and balance of plant infrastructure.
Front end engineering study to evaluate a deficient vacuum system at an existing ag-based thermoforming facility, including quantifying baseline operation conditions and evaluating potential system improvement modifications.
Comprehensive structural inspection and due diligence reporting for fleet of 15+ production and distribution facilities, working to identify immediate risks to market supply.
Isomer provided detailed design engineering, permitting, and construction support for a $60 million 50 MW-DC solar facility located on 365-acres in Idaho.
Front-end engineering and project development support for a 450,000 TPA greenfield wood pellet plant. Roundwood and residuals were used for feedstock. Facility included rotary drying, rail and truck loadout capability.
This effort included developing a comprehensive independent engineering report to assess a biosolids-only downdraft gasification system. The gasification system is located in a repurposed building adjacent to a local sewage authority...
This effort included the completion of the conceptual design (FEL2) phase for a $5 million USD water sustainability program for an existing Fiber Optics facility with a goal to reduce water consumption at the site by 80%.
Front-end engineering and project development services to determine feasibility and conceptual layout for 314 MW-DC solar facility located on 2,040-acres in Utah.
This effort included the detailed design, permitting, and construction support for the balance of plant (BOP) systems on a 1400 BPD facility converting woody biomass into renewable fuels.