FEL2 front-end engineering design for a first-of-a-kind 1000TPA facility to recover monomers from spent textiles via a proprietary chemical recycling process, including scale-up from an existing lab-scale processes.
Isomer provided detailed design engineering, permitting, and construction support for a renewable natural gas facility located at the Anson County Landfill.
Detailed design engineering in a design-build arrangement for a 60,000 SF roll finishing and shipping warehouse install at an existing pulp & paper mill as part of a major modernization effort.
This effort included the FEED, detailed design, permitting, and construction support for a 6500 BPD Renewable Diesel Plant, utilizing Haldor Topsoe technology.
Root cause analysis for a significant vibration issue affecting a group of dryer cans on an existing paper machine, including both onsite and offsite analysis.
Pre-FEL study and FEL1 design of a primarily greenfield 150TPD ag-based pulp molded fiber facility, including feedstock handling and separation, material storage, semi-chem pulping, stock preparation, and molding.
Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
Civil engineering design, permit coordination, and construction administration for the development of a 1.9-acre outparcel for a dental office utilizing a common pond for stormwater detention.
Front-end engineering for the addition of a 3,000 TPY rolled ornamental stainless steel, high-frequency production line at an existing rolled tubes production facility.