This effort included the FEL3 and detailed design for a new reactor structure, associated equipment and supporting insfras turecture at an existing surfactant production facility.
Structural detailed design for a clinker cooler retrofit, including steel and concrete modifications to support a new 200HP ID fan and associated ductwork.
This project included detailed design and procurement support for the main polysilicon production building, the largest project on the campus of a multi-billion-dollar greenfield manufacturing site...
Designing temporary construction facilities on a constrained worksite, including a lunch/break tent over an existing ditch line, to support the EPC contractor's construction of new HRSG units at an existing generating station.
This effort included the basic design (FEL1-2) phase for a greenfield $37 million USD Lithium-Ion Battery recycling facility. The owner operates facilities throughout Asia and Europe and this facility is their first in the United States.
Conceptual site planning for a portfolio of parcels to complete test fits of commercial developments, generating concept plans, layouts, and imagery for use in marketing materials.
Detailed design engineering for a 10-foot diameter downcomer duct replacement project in an existing 250-foot tall preheater tower, including significant structural reinforcements.
FEL1 Engineering and Owner’s Engineering Services for a 170 TPD Tissue Machine Dry End Replacement project including the Yankee Dryer, Hood, and Air System, as part of a Fleet-wide Rebuild Program.
FEL3 engineering package for the installation of two new reactors to replace an existing end-of-life reactor vessel at a specialty chemicals facility.
This scope consisted of multiple layers of support for the re-development of a 48 MW biomass-fired power plant that had been moth-balled in the middle of the initial construction process. As the project found new life...