FEL1 and capital cost estimate development for the addition of a hydrocyclone cleaner to protect refiners from contaminants at an existing 30TPD ag-based pulping line.
Front-end engineering services for a pelletized corn stover feedstock facility supporting sustainable aviation fuel production, including material balance development, high-level equipment sizing, and a feasibility-level site layout.
FEL1 Engineering and Owner’s Engineering Services for a 160 TPD Tissue Machine Rebuild project to convert from Towel-grade to Tissue-grade and increase production capacity as part of a Fleet-wide Rebuild Program.
Civil engineering design, permit coordination, and construction administration for the development of a 1.2-acre site for an 3,000-sf Zaxby's quick service restaurant.
Detailed design, procurement, and construction support for a $300 million brownfield, 100% recycled (OCC) linerboard machine installation to produce premium and back ply liner.
Isomer completed project technical and financial due diligence on a series of 19 projects producing renewable natural gas (RNG) from anaerobic digestion to support a private equity firm.
FEL3 engineering package for the installation of two new reactors to replace an existing end-of-life reactor vessel at a specialty chemicals facility.
This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
Isomer provided detailed design for a $6 million battery storage project to enhance grid stability by providing additional capacity during times of peak consumption for the city utility.
This effort included the FEED, detailed design, permitting, and construction support for a 6500 BPD Renewable Diesel Plant, utilizing Haldor Topsoe technology.