Technical due diligence for a financier on a Waste Heat to Power asset in construction to support financial close, as well as an evaluation of the company's development pipeline.
FEL2 through detail design engineering for a velvet manufacturer facility relocation. Scope of work included a site walk down, equipment and facility studies, 3D modeling (including VR walkthrough), heavy civil coordination, and wetlands study.
FEL1 and detailed design to double the capacity of an existing ag-pulp feedstock processing line, including modifications to material handling, hammer mill, pneumatic transport, and conveying systems.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
Civil engineering, permit coordination, and construction administration for the re-development of a 0.73-acre existing commercial site for the construction of a Starbucks coffee house.
Civil engineering design and permit coordination services for relocation of an existing sanitary sewer main to accommodate construction of a proposed retaining wall.
This effort included developing a comprehensive independent engineering report to assess a biosolids-only downdraft gasification system. The gasification system is located in a repurposed building adjacent to a local sewage authority...
This project focused on installation a new 1 million gallon molten sulfur tank in an existing sulfuric acid production facility. The design including supporting piping electrical and structural modifications.
FEL1 and FEL2 Engineering and Owner’s Engineering Services for a 170 TPD Tissue Machine Dry End Replacement project including the Yankee Dryer, Hood, and Air System, as part of a Fleet-wide Rebuild Program.
Preliminary and detailed design engineering to evaluate an existing equipment structure experiencing excessive dynamic loading and responses, determine the root cause, and develop a remediation plan.