Technical due diligence for a financier on a Waste Heat to Power asset in construction to support financial close, as well as an evaluation of the company's development pipeline.
FEL2 through detail design engineering for a velvet manufacturer facility relocation. Scope of work included a site walk down, equipment and facility studies, 3D modeling (including VR walkthrough), heavy civil coordination, and wetlands study.
FEL1 and detailed design to double the capacity of an existing ag-pulp feedstock processing line, including modifications to material handling, hammer mill, pneumatic transport, and conveying systems.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
Conceptual site planning for a portfolio of parcels to complete test fits of commercial developments, generating concept plans, layouts, and imagery for use in marketing materials.
FEL2 engineering and cost estimating for a containerboard machine rebuild project including forming, press, dryer, and vacuum system upgrades to improve sheet quality, efficiency, and production.
This project included a contract for detailed design following a transition from another engineering firm at less than 10% complete; however, construction activities had already begun in the field. The scope of the project...
Front-end engineering services for a pelletized corn stover feedstock facility supporting sustainable aviation fuel production, including material balance development, high-level equipment sizing, and a feasibility-level site layout.
Detailed design engineering for replacement of an existing 240V MCC with a new 480V MCC at a specialty chemical facility, including relocation and refeed of wall-mounted loads to the new MCC.
Detailed design and project management for a $100 million, 2,000 MTPD Semi-Dry Cement Plant upgrade, featuring a new pyroline, at an existing facility in Oklahoma.