Isomer provided full-service FEL3 Engineering for a new ferric chloride production process at an existing specialty chemicals facility, including heat and material and layout development.
Front-end engineering services for a pelletized bagasse feedstock facility supporting sustainable aviation fuel production at a co-located sugar mill, including bagasse handling, drying, pelletizing, utility upgrades, and carbon capture.
Detailed design and structural dynamics engineering evaluation to analyze a 4000-hp existing power plant ID fan for an unbalance issue at an existing facility.
Detailed design engineering to support the installation of a new rotary strainer for a milling tandem at an operating sugar mill, including a new steel structure and foundation constructed in a heavy brownfield environment.
Front-end engineering and project development services to determine feasibility and order of magnitude costs for a greenfield facility with 150MW Electrolyzers and balance of plant infrastructure.
New kraft liner machine and building, OCC facility, highly modified fiberline, boiler natural gas conversion, and electrical infrastructure additions to accommodate virgin and recycled fiber linerboard production.
This project included a contract for detailed design following a transition from another engineering firm at less than 10% complete; however, construction activities had already begun in the field. The scope of the project...
FEL1 study for a 6 ktpa battery-grade phosphoric acid plant co-located with 10 ktpa sulfuric acid facility, including process validation and several alternatives analyses.
Pre-FEL study and FEL1 design of a primarily greenfield 150TPD ag-based pulp molded fiber facility, including feedstock handling and separation, material storage, semi-chem pulping, stock preparation, and molding.
Technical due diligence of an existing biomanufacturing company facility including review of process, facility, operations, and overall project execution.