This effort included the detailed design, permitting, and on-site construction support for a $75 million greenfield plant to produce food-grade vegetable oil.
This effort included the FEED package, detailed design, and construction support for restarting an existing Paper Machine and supporting systems and infrastructure at a legacy mill.
Preliminary engineering in support of a developer commercializing a first-of-a-kind process to capture and store CO2 via natural water sources adjacent to industrial point source emitters.
Detailed design engineering for a 10-foot diameter downcomer duct replacement project in an existing 250-foot tall preheater tower, including significant structural reinforcements.
Detailed Design Engineering for a new electrolysis hydrogen generation system to inject hydrogen and oxygen into existing kiln burner fuel and combustion air lines, respectively.
Comprehensive site logistics study to evaluate and improve inbound and outbound truck routing for a cement manufacturing facility to relieve heavy onsite traffic congestion.
Detailed design for a maintenance and reliability project on an existing linerboard machine, including improvements for the existing tail cutter system to reduce damage to felts and improve overall machine runnability.
FEL1 Engineering and Site Selection services for a 200,000 TPY, First-of-its-Kind, Commercial Scale Facility to manufacture Ultra-low-Carbon Cement, co-located at an existing cement plant.
Development of a strategic capital expenditure (CAPEX) spending plan to guide the allocation of approximately $50MM for an Owner with a mill in excess of 60 years of age.