FEL2 Engineering and Owner’s Engineering Services for a 280 TPD Tissue Machine Process Air System Replacement project as part of a Fleet-wide Rebuild Program.
Front-end engineering study for a new low consistency storage tower and pump integrated into an existing 30 TPD ag-based fiber pulping process facility.
Performed third-party engineering due diligence to identify major risks and red flags for a project installing a Textile Recycling Facility into an existing mothballed manufacturing facility.
This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
New kraft liner machine and building, OCC facility, highly modified fiberline, boiler natural gas conversion, and electrical infrastructure additions to accommodate virgin and recycled fiber linerboard production.
Detailed design and FEL2 for a 25 TPD molded fiber production facility. Design included new repulping, stock prep, thermoforming, and utility systems located in an existing manufacturing facility.
FEL2 front-end engineering design to evaluate a deficient vacuum seal water cooling loop at an existing molded fiber facility and replace an undersized cooling tower and supply pumps.
Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
Front end engineering design and technology trials support for a liquor coproduct contaminant reduction system at an existing 30TPD ag-based pulp mill.