This project focused on installation a new 1 million gallon molten sulfur tank in an existing sulfuric acid production facility. The design including supporting piping electrical and structural modifications.
Detailed design and FEL2 for a 25 TPD molded fiber production facility. Design included new repulping, stock prep, thermoforming, and utility systems located in an existing manufacturing facility.
This project included detailed design and procurement support for the main polysilicon production building, the largest project on the campus of a multi-billion-dollar greenfield manufacturing site...
Front end engineering, detailed design, and Project Management and Construction Oversight services for a $3MM TIC project to expand an existing vacuum system at a 25 TPD ag-based pulp thermoforming facility.
This effort included the front-end engineering, detailed design, and construction oversight to convert all machine DC motors and drives to AC power. The PIVs were also replaced with AC motors.
This effort included detailed engineering on a four project Anaerobic Digestion to biogas program with site locations in Georgia and California. The facilities were located on existing dairy farms of approximately 12,000 cows each...
The effort included the detailed design and construction oversight over the winder rebuild of the paper machine, which included new safety systems, slitter, feeding and gluing capabilities.
Structural detailed design for a clinker cooler retrofit, including steel and concrete modifications to support a new 200HP ID fan and associated ductwork.
Detailed design, procurement, and construction support for a $300 million brownfield, 100% recycled (OCC) linerboard machine installation to produce premium and back ply liner.
Detailed design including site development, foundations, electrical, and mechanical design for a 40,000SF maintenance warehouse built to service steel processing equipment