Structural feasibility study to evaluate the potential addition of rooftop solar panels to multiple existing structures at a chemicals manufacturing facility, as well as the potential for adding panels over existing stormwater infrastructure.
FEL2 front-end engineering design to evaluate a deficient vacuum seal water cooling loop at an existing molded fiber facility and replace an undersized cooling tower and supply pumps.
FEL1 preliminary engineering design for a first-of-a-kind 1KTPA facility to produce Cathode Active Materials for EV batteries, including scale-up from an existing lab-scale processes.
FEL3 Engineering package supporting the Balance of Plant design and integration of a vendor-supplied 4.0 MGD Wastewater Treatment System into an existing linerboard mill.
Front end engineering study to evaluate a deficient vacuum system at an existing ag-based thermoforming facility, including quantifying baseline operation conditions and evaluating potential system improvement modifications.
This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
Detailed design and FEL2 for a 25 TPD molded fiber production facility. Design included new repulping, stock prep, thermoforming, and utility systems located in an existing manufacturing facility.
This effort included the completion of the conceptual design (FEL2) phase for a $5 million USD water sustainability program for an existing Fiber Optics facility with a goal to reduce water consumption at the site by 80%.
Front-end engineering and project development services to determine feasibility and conceptual layout for 314 MW-DC solar facility located on 2,040-acres in Utah.