Preliminary engineering support of a first-of-its-kind ag-based pulping and thermoforming facility, including heat & material balance development and other key activities.
New kraft liner machine and building, OCC facility, highly modified fiberline, boiler natural gas conversion, and electrical infrastructure additions to accommodate virgin and recycled fiber linerboard production.
FEL1 and detailed design to double the capacity of an existing ag-pulp feedstock processing line, including modifications to material handling, hammer mill, pneumatic transport, and conveying systems.
This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
Front-end engineering and project development services to determine feasibility and order of magnitude costs for a greenfield facility with 150MW Electrolyzers and balance of plant infrastructure.
This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
Preliminary engineering services in support of a thermoforming capacity increase at an existing molded fiber production facility, including a cost-benefit analysis and extensive utility study.
Front-end engineering study for a new low consistency storage tower and pump integrated into an existing 30 TPD ag-based fiber pulping process facility.
FEL-2 Engineering for the ISBL area of a 12,000 TPA proprietary electrolyte production facility, including all process, piping, and instrumentation & controls design.
This effort included the detailed design and procurement support for a $400 million brownfield through-air-drying (TAD) tissue machine installation and supporting infrastructure. The facility design included all processes necessary...