This effort included the detailed design and procurement support for a $250 million brownfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary to produce premium quality parent rolls..
The effort included the front-end engineering and detailed design services for installing a 15 TPD Green Hydrogen Production and Liquefaction Plant on a greenfield site.
Structural feasibility study to evaluate the potential addition of rooftop solar panels to multiple existing structures at a chemicals manufacturing facility, as well as the potential for adding panels over existing stormwater infrastructure.
Isomer provided full-service FEL3 Engineering for a new ferric chloride production process at an existing specialty chemicals facility, including heat and material and layout development.
Civil engineering, permit coordination, and construction administration for the development of 365-acres of existing agricultural land for a 50 MW-DC solar facility.
The project included front-end engineering and detailed design for a multi-year facility expansion at a honeycomb scrubber plant to facilitate a six-fold increase in production capacity.
Root cause analysis for a significant vibration issue affecting a group of dryer cans on an existing paper machine, including both onsite and offsite analysis.
Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
Front end engineering study to evaluate the feasibility of installing pressure screening systems on existing stock approach loops at an ag-based pulp thermoforming facility.
Conceptual civil engineering and site plan development to support the preliminary plan approval for a 12,000-square foot indoor pickleball and badminton facility.