FEL1 and detailed design to double the capacity of an existing ag-pulp feedstock processing line, including modifications to material handling, hammer mill, pneumatic transport, and conveying systems.
FEL2 front-end engineering design to evaluate a deficient vacuum seal water cooling loop at an existing molded fiber facility and replace an undersized cooling tower and supply pumps.
Front end engineering study to evaluate a deficient vacuum system at an existing ag-based thermoforming facility, including quantifying baseline operation conditions and evaluating potential system improvement modifications.
This effort included the basic design (FEL1-2) phase for a greenfield $37 million USD Lithium-Ion Battery recycling facility. The owner operates facilities throughout Asia and Europe and this facility is their first in the United States.
Existing mill conversion from fine paper to linerboard production using 100% OCC furnish including new OCC facility and warehouse, conversion of existing machine, conversion of two boilers, and other utility upgrades.
Front-end engineering and project development services to determine feasibility and conceptual layout for 400 MW-DC solar facility with 200-MW BESS located in Nebraska.
This effort included the detailed design and construction support to install a River Water Intake System and Raw Water Treatment system to support an Ammonium Nitrate Solution (ANSol) plant in Tennessee.
Capital cost estimating and detailed design engineering for a $5MM TIC project to upgrade dry end handling capabilities at an existing chemicals facility.
FEL1 preliminary engineering design for a first-of-a-kind 1KTPA facility to produce Cathode Active Materials for EV batteries, including scale-up from an existing lab-scale processes.
This effort included the FEL3 and detailed design for a new reactor structure, associated equipment and supporting insfras turecture at an existing surfactant production facility.