Structural feasibility study to evaluate the potential addition of rooftop solar panels to multiple existing structures at a chemicals manufacturing facility, as well as the potential for adding panels over existing stormwater infrastructure.
Root cause analysis for a significant vibration issue affecting a group of dryer cans on an existing paper machine, including both onsite and offsite analysis.
The scope of this effort consisted of front-end engineering for a significant capacity increase for an existing polymer facility. The facility produces high-performance elastomers used as replacements for rubber. The project team...
Isomer provided process engineering design and consulting services in support of an OEM’s proprietary pyrolysis skid designed to convert municipal solid waste (MSW) into an enhanced syngas stream for sustainable aviation fuel (SAF) production.
FEL1 and capital cost estimate development for the addition of a hydrocyclone cleaner to protect refiners from contaminants at an existing 30TPD ag-based pulping line.
FEL2 front-end engineering design to evaluate a deficient vacuum seal water cooling loop at an existing molded fiber facility and replace an undersized cooling tower and supply pumps.
This effort included the completion of the conceptual design (FEL2) phase for a $5 million USD water sustainability program for an existing Fiber Optics facility with a goal to reduce water consumption at the site by 80%.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
FEL1 engineering design for a novel critical elements recovery facility funded by ARPA-e to process 1 ktpd of ultramafic tailings, integrating direct air capture of CO2 for carbon sequestration and electrolytic production of sulfuric acid.
This scope consisted of multiple layers of support for the re-development of a 48 MW biomass-fired power plant that had been moth-balled in the middle of the initial construction process. As the project found new life...