FEL-2 design to support upgrades to an existing linerboard paper machine roll handling line, including conveyors, a lowerator, and shipping floor conveyors for loading finished product rolls into railcars.
FEL3 Engineering package supporting the Balance of Plant design and integration of a vendor-supplied 4.0 MGD Wastewater Treatment System into an existing linerboard mill.
Preliminary cost modeling in support of a developer with novel turbine technology intended to be retrofitted or incorporated into chillers for data centers to increase performance.
Detailed design engineering for a $45MM TIC laser guided vehicle operated distribution center at an existing sugar mill and refinery, including the integration into an existing warehouse and packaging building.
This project included a contract for detailed design following a transition from another engineering firm at less than 10% complete; however, construction activities had already begun in the field. The scope of the project...
Civil engineering design and development to support for the conceptual (30%) design of a 75 MW-DC solar facility located on 330-acres in Nevada located within heavy floodplains.
Detailed design and structural dynamics engineering evaluation to analyze an existing paper machine dryer section for an unbalance issue at an existing facility.
Civil engineering design, permit coordination, and construction administration for a commercial office park development, master planned to be anchored by a medical office with five (5) accessory building pads for a total 40,000-sf.
FEL1 Engineering and Owner’s Engineering Services for a 160 TPD Tissue Machine Rebuild project to convert from Towel-grade to Tissue-grade and increase production capacity as part of a Fleet-wide Rebuild Program.