Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
Front end engineering design and technology trials support for a liquor coproduct contaminant reduction system at an existing 30TPD ag-based pulp mill.
FEL2 front-end engineering design for a first-of-a-kind 1000TPA facility to recover monomers from spent textiles via a proprietary chemical recycling process, including scale-up from an existing lab-scale processes.
The scope of this effort consisted of front-end engineering for a significant capacity increase for an existing polymer facility. The facility produces high-performance elastomers used as replacements for rubber. The project team...
Front-end engineering and project development services to determine feasibility and conceptual layout for 400 MW-DC solar facility with 200-MW BESS located in Nebraska.
This effort centered around providing early-stage project development services for a brownfield wood pellet plant rated at 150,000 metric tons per year. Residuals from nearby sawmills made up all of the feedstock used for this project. ..
Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
This effort included the detailed design, permitting, and construction support for the balance of plant (BOP) systems on a 1400 BPD facility converting woody biomass into renewable fuels.
Front-end engineering services and project development support for a new three stage feedstock cleaning/storage system at an existing non-wood ag-based pulping and molding facility.