Owner’s Engineering and support during the pre-FID engineering phase (FEL3) for a new 20 million gallons per year Renewable Fuel Oil Production Facility.
Civil engineering design, permit coordination, and construction administration for the development of a 1.2-acre site for an 3,000-sf Zaxby's quick service restaurant.
Detailed design, procurement, and construction (EPC) services for a $130 million greenfield bio-energy center to generate cellulosic ethanol from yard and wood waste.
The project included front-end engineering and detailed design for a multi-year facility expansion at a honeycomb scrubber plant to facilitate a six-fold increase in production capacity.
FEL2 preliminary study and detailed design engineering for a new concrete containment area for chemical railcar loading at an existing production facility.
This $150 million scope consisted of conceptual engineering, front-end engineering, and detailed design to meet an issued environmental consent decree at three similar yet unique metallurgical coking facilities...
Heat and Material Balance (HMB) study and preliminary vendor engagement for a 9 MW biomass-to-power generation facility utilizing gasification to produce syngas and biochar, coupled with an ORC system for power generation.
Front-end engineering services for a pelletized bagasse feedstock facility supporting sustainable aviation fuel production at a co-located sugar mill, including bagasse handling, drying, pelletizing, utility upgrades, and carbon capture.
This scope consisted of multiple layers of support for the re-development of a 48 MW biomass-fired power plant that had been moth-balled in the middle of the initial construction process. As the project found new life...
Isomer provided conceptual site layout, permitting, and conditional use application support for a portfolio of solar, battery storage, and hydrogen facilities across the US.