FEL2 Engineering and Owner’s Engineering Services for a 180 TPD Tissue Machine Yankee Dryer Hood Replacement project as part of a Fleet-wide Rebuild Program.
This effort included the detailed design and procurement support for a $250 million brownfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary to produce premium quality parent rolls..
Comprehensive site logistics study to evaluate and improve inbound and outbound truck routing for a cement manufacturing facility to relieve heavy onsite traffic congestion.
Detailed design and engineering services for a $45 million containerboard machine rebuild project at an existing facility featuring a new shoe press and an iTable to replace the existing top-wire former.
FEL-2 Engineering for the ISBL area of a 12,000 TPA proprietary electrolyte production facility, including all process, piping, and instrumentation & controls design.
Front-end engineering study for a new low consistency storage tower and pump integrated into an existing 30 TPD ag-based fiber pulping process facility.
Civil engineering, permit coordination, and construction administration to support the re-development of a 2.3-acre overflow parking lot at an existing car dealership, including the construction of a new dedicated service shop (8,800-sf).
Root cause analysis for a significant vibration issue affecting a group of dryer cans on an existing paper machine, including both onsite and offsite analysis.
Detailed design, procurement, and construction (EPC) services for a $300 million coal-fired power plant regulatory program including fly ash, bottom ash, and water management conversions.
Detailed Design, Procurement, and Construction (EPC) services for a $130 million greenfield bio-energy center to generate cellulosic ethanol from yard and wood waste.