This effort included the FEED package, detailed design, and construction support for restarting an existing Paper Machine and supporting systems and infrastructure at a legacy mill.
Front-end engineering and project development services to determine feasibility and order of magnitude costs for a greenfield facility with 150MW Electrolyzers and balance of plant infrastructure.
This effort included developing a comprehensive independent engineering report to assess a biosolids-only downdraft gasification system. The gasification system is located in a repurposed building adjacent to a local sewage authority...
This effort included detailed design mechanical, piping, electrical and structural services to support a $500 million expansion to add two new sustainable technology product lines at an existing automotive manufacturing facility.
The effort included the detailed design and construction oversight over the winder rebuild of the paper machine, which included new safety systems, slitter, feeding and gluing capabilities.
Fluff Pulp Machine Upgrade Project with the objective to increase production of the paper machine through machine and other auxiliary system modifications.
This effort included the detailed design, permitting, and on-site construction support for a $75 million greenfield plant to produce food-grade vegetable oil.
This project included front-end engineering and project development support for a brownfield non-wood ag-based pulping and molding facility. The facility was designed to provide a finished product capacity of 15,000 bone-dry metric tons per year...
Isomer completed project technical and financial due diligence on a series of 19 projects producing renewable natural gas (RNG) from anaerobic digestion to support a private equity firm.
Owner’s Engineering and support during the pre-FID engineering phase (FEL3) for a new 20 million gallons per year Renewable Fuel Oil Production Facility.