Detailed design and project management for a $100 million, 2,000 MTPD Semi-Dry Cement Plant upgrade, featuring a new pyroline, at an existing facility in Oklahoma.
This project effort included detailed design and construction support for a turnkey, full-scale Ethylene Oxide production facility along the Delaware River.
Detailed design for rerouting broke from an existing linerboard machine to the OCC system to improve water balance, remove fines, and increase fiber recovery.
Full-service conceptual design FEL2 services for the infrastructure project to support the Lithium Battery-grade 47ktpa Refrigerant and 10ktpa Electrolyte Facility Expansion projects at an existing chemicals plant in the southeast.
Comprehensive structural inspection and due diligence reporting for fleet of 15+ production and distribution facilities, working to identify immediate risks to market supply.
This project included a contract for detailed design following a transition from another engineering firm at less than 10% complete; however, construction activities had already begun in the field. The scope of the project...
This effort included the completion of the conceptual design (FEL2) phase for a $5 million USD water sustainability program for an existing Fiber Optics facility with a goal to reduce water consumption at the site by 80%.
This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
Detailed design engineering for a $45MM TIC laser guided vehicle operated distribution center at an existing sugar mill and refinery, including the integration into an existing warehouse and packaging building.