FEL2 Engineering and Owner’s Engineering Services for a 280 TPD Tissue Machine Process Air System Replacement project as part of a Fleet-wide Rebuild Program.
This effort included the FEL3 and detailed design for a new reactor structure, associated equipment and supporting insfras turecture at an existing surfactant production facility.
FEL3 engineering package for the installation of two new reactors to replace an existing end-of-life reactor vessel at a specialty chemicals facility.
This effort included the front-end engineering, detailed design, and construction oversight to convert all machine DC motors and drives to AC power. The PIVs were also replaced with AC motors.
Civil engineering, permit coordination, and construction administration for the re-development of a 0.73-acre existing commercial site for the construction of a Starbucks coffee house.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
This effort included detailed engineering on a four project Anaerobic Digestion to biogas program with site locations in Georgia and California. The facilities were located on existing dairy farms of approximately 12,000 cows each...
FEL1 and capital cost estimate development for the addition of a hydrocyclone cleaner to protect refiners from contaminants at an existing 30TPD ag-based pulping line.
FEL1 engineering design for a novel critical elements recovery facility funded by ARPA-e to process 1 ktpd of ultramafic tailings, integrating direct air capture of CO2 for carbon sequestration and electrolytic production of sulfuric acid.
The effort included the detailed design and construction oversight over the winder rebuild of the paper machine, which included new safety systems, slitter, feeding and gluing capabilities.