Front-end engineering and project development services to assist developer in determining the feasibility and estimated construction cost of various projects throughout the upstate of South Carolina.
Front-end engineering and project development support for a 450,000 TPA greenfield wood pellet plant. Roundwood and residuals were used for feedstock. Facility included rotary drying, rail and truck loadout capability.
Front end engineering study to evaluate the feasibility of firing a secondary biomass fuel in three separate biomass boilers at an existing facility in an effort to reduce the consumption of the primary fuel source.
Detailed design, procurement, and construction (EPC) services for a $130 million greenfield bio-energy center to generate cellulosic ethanol from yard and wood waste.
FEL3 front-end engineering design for a proprietary bioprocessing facility to utilize specially engineered microorganisms to synthesize bio-based chemicals and produce sustainable commodity products using renewable raw materials, like sugar.
Fluff Pulp Machine Upgrade Project with the objective to increase production of the paper machine through machine and other auxiliary system modifications.
This scope consisted of multiple layers of support for the re-development of a 48 MW biomass-fired power plant that had been moth-balled in the middle of the initial construction process. As the project found new life...
Performed third-party engineering due diligence to identify major risks and red flags for a project installing a Textile Recycling Facility into an existing mothballed manufacturing facility.
Front-end engineering and project development services to determine feasibility and conceptual layout for 210 MW-DC solar facility located in Arizona.
Project management and construction oversight for an $8 million chemical manufacturing facility upgrade, including direct supervision of detailed design and construction bid process.