FEL2 preliminary study and detailed design engineering for a new concrete containment area for chemical railcar loading at an existing production facility.
This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
Detailed design and project management support for the installation of electric semi-truck charging stations at a portfolio of sites across California.
Technical due diligence on behalf of a financier for an existing soil washing asset in operation, as well as a forward-looking evaluation of the company's pipeline of development opportunities.
FEL1 study for a 6 ktpa battery-grade phosphoric acid plant co-located with 10 ktpa sulfuric acid facility, including process validation and several alternatives analyses.
Owner’s Engineering and support during the pre-FID engineering phase (FEL3) for a new 20 million gallons per year Renewable Fuel Oil Production Facility.
Designing temporary construction facilities on a constrained worksite, including a lunch/break tent over an existing ditch line, to support the EPC contractor's construction of new HRSG units at an existing generating station.
Civil engineering, permit coordination, and construction administration for the removal and replacement of an deteriorated parking lot with a 107,500-sf light industrial building.
Isomer provided detailed design for a $6 million battery storage project to enhance grid stability by providing additional capacity during times of peak consumption for the city utility.
FEL1 and FEL2 Engineering and Owner’s Engineering Services for a 170 TPD Tissue Machine Dry End Replacement project including the Yankee Dryer, Hood, and Air System, as part of a Fleet-wide Rebuild Program.