Detailed design including site development, foundations, electrical, and mechanical design for a 40,000SF maintenance warehouse built to service steel processing equipment
This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
Civil engineering design, permit coordination, and construction administration for a commercial office park development, master planned to be anchored by a medical office with five (5) accessory building pads for a total 40,000-sf.
This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
This project included a contract for detailed design following a transition from another engineering firm at less than 10% complete; however, construction activities had already begun in the field. The scope of the project...
Civil engineering design and development to support for the conceptual (30%) design of a 75 MW-DC solar facility located on 330-acres in Nevada located within heavy floodplains.
Detailed design and structural dynamics engineering evaluation to analyze an existing paper machine dryer section for an unbalance issue at an existing facility.
FEL1 Engineering and Owner’s Engineering Services for a 160 TPD Tissue Machine Rebuild project to convert from Towel-grade to Tissue-grade and increase production capacity as part of a Fleet-wide Rebuild Program.
FEL3 Engineering package supporting the Balance of Plant design and integration of a vendor-supplied 4.0 MGD Wastewater Treatment System into an existing linerboard mill.