This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
FEED and Detailed Design Engineering for a new tank farm with 300,000 gallons of total capacity to store a combination of Class I, II, and III flammable and combustible liquids.
Performed third-party engineering due diligence to identify major risks and red flags for a project installing a Textile Recycling Facility into an existing mothballed manufacturing facility.
Detailed design including site development, foundations, electrical, and mechanical design for a 40,000SF maintenance warehouse built to service steel processing equipment
Front-end engineering study for a new low consistency storage tower and pump integrated into an existing 30 TPD ag-based fiber pulping process facility.
FEL1 and detailed design to double the capacity of an existing ag-pulp feedstock processing line, including modifications to material handling, hammer mill, pneumatic transport, and conveying systems.
Detailed design and structural dynamics engineering evaluation to analyze a 4000-hp existing power plant ID fan for an unbalance issue at an existing facility.
This scope consisted of front-end engineering and detailed design to increase the bark firing capacity of an existing combination boiler at a paper mill. Initial studies identified issues, and the project team proceeded...
This effort included the detailed design and procurement support for a $250 million brownfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary to produce premium quality parent rolls..