Red Flags Analysis report in support of client’s potential investment in a polystyrene recycling company and the planned scale up of their demonstration-level facility to a commercial scale.
Front end engineering study to evaluate the feasibility of installing pressure screening systems on existing stock approach loops at an ag-based pulp thermoforming facility.
This scope consisted of multiple layers of support for the re-development of a 48 MW biomass-fired power plant that had been moth-balled in the middle of the initial construction process. As the project found new life...
Front end engineering study to evaluate the feasibility of firing a secondary biomass fuel in three separate biomass boilers at an existing facility in an effort to reduce the consumption of the primary fuel source.
This effort included the detailed design, permitting, and construction support for a $400 million, 850,000 sq. foot state of the art particleboard manufacturing plant.
Detailed Design Engineering for a new electrolysis hydrogen generation system to inject hydrogen and oxygen into existing kiln burner fuel and combustion air lines, respectively.
FEL1 and detailed design to double the capacity of an existing ag-pulp feedstock processing line, including modifications to material handling, hammer mill, pneumatic transport, and conveying systems.
Civil engineering design, permit coordination, and construction administration for the development of a 1.2-acre site for an 3,000-sf Zaxby's quick service restaurant.
Preliminary engineering support for a site logistics study at an operating cement manufacturing plant to improve truck circulation and loadout efficiency at finished cement silos.
Multi-discipline front-end engineering and estimating services for a facility using a proprietary process to convert waste cellulose into consumer product replacements.