Red Flags Analysis report in support of client’s potential investment in a polystyrene recycling company and the planned scale up of their demonstration-level facility to a commercial scale.
Front end engineering study to evaluate the feasibility of installing pressure screening systems on existing stock approach loops at an ag-based pulp thermoforming facility.
This scope consisted of multiple layers of support for the re-development of a 48 MW biomass-fired power plant that had been moth-balled in the middle of the initial construction process. As the project found new life...
Front end engineering study to evaluate the feasibility of firing a secondary biomass fuel in three separate biomass boilers at an existing facility in an effort to reduce the consumption of the primary fuel source.
Structural detailed design for a clinker cooler retrofit, including steel and concrete modifications to support a new 200HP ID fan and associated ductwork.
The effort included the detailed design and construction oversight over the winder rebuild of the paper machine, which included new safety systems, slitter, feeding and gluing capabilities.
This effort included the FEED, detailed design, permitting, and construction support for a 6500 BPD Renewable Diesel Plant, utilizing Haldor Topsoe technology.
Project management and Owner's Engineering in support of an FEL-3 study to convert an existing paper machine from newsprint to liner board and medium grades. The scope included a new OCC plant, new steam turbine, and a full paper machine rebuild.
Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
Front-end engineering and project development services to determine feasibility and conceptual layout for 400 MW-DC solar facility with 200-MW BESS located in Nebraska.