Preliminary engineering support for a site logistics study at an operating cement manufacturing plant to improve truck circulation and loadout efficiency at finished cement silos.
Performed third-party engineering due diligence to identify major risks and red flags for a project installing a Textile Recycling Facility into an existing mothballed manufacturing facility.
This effort included the detailed design, permitting, and construction support for a $400 million, 850,000 sq. foot state of the art particleboard manufacturing plant.
This project focused on installation a new 1 million gallon molten sulfur tank in an existing sulfuric acid production facility. The design including supporting piping electrical and structural modifications.
This project included a contract for detailed design following a transition from another engineering firm at less than 10% complete; however, construction activities had already begun in the field. The scope of the project...
Conceptual and detailed design engineering, permitting, and construction support for a $15 million 10 MW-DC solar facility located on 50-acres in California.
FEL1 and capital cost estimate development for the addition of a hydrocyclone cleaner to protect refiners from contaminants at an existing 30TPD ag-based pulping line.
FEL-2 and full-service detailed design engineering of the ISBL scope for a Dry Bagging expansion at an existing drywall compound manufacturing facility.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
Capital cost estimating and detailed design engineering for a $5MM TIC project to upgrade dry end handling capabilities at an existing chemicals facility.