FEL1 and capital cost estimate development for the addition of a hydrocyclone cleaner to protect refiners from contaminants at an existing 30TPD ag-based pulping line.
Front end engineering, detailed design, and Project Management and Construction Oversight services for a $3MM TIC project to expand an existing vacuum system at a 25 TPD ag-based pulp thermoforming facility.
Civil engineering, permit coordination, and construction administration for the re-development of a 0.73-acre existing commercial site for the construction of a Starbucks coffee house.
The scope of this effort consisted of front-end engineering for a significant capacity increase for an existing polymer facility. The facility produces high-performance elastomers used as replacements for rubber. The project team...
Front-end engineering and project development services to determine feasibility and order of magnitude costs for a greenfield facility with 150MW Electrolyzers and balance of plant infrastructure.
The project included front-end engineering and detailed design for a multi-year facility expansion at a honeycomb scrubber plant to facilitate a six-fold increase in production capacity.
This effort included the detailed design and construction support to install a River Water Intake System and Raw Water Treatment system to support an Ammonium Nitrate Solution (ANSol) plant in Tennessee.
FEL1 and detailed design to double the capacity of an existing ag-pulp feedstock processing line, including modifications to material handling, hammer mill, pneumatic transport, and conveying systems.
FEL2 front-end engineering design to evaluate a deficient vacuum seal water cooling loop at an existing molded fiber facility and replace an undersized cooling tower and supply pumps.
Project Management and Construction Oversight services for a 15TPD ag-based fiber thermoforming line retrofit, including demolition of old equipment and design/installation of new equipment.