FEL2 through detail design engineering for a velvet manufacturer facility relocation. Scope of work included a site walk down, equipment and facility studies, 3D modeling (including VR walkthrough), heavy civil coordination, and wetlands study.
FEL2 front-end engineering design for a first-of-a-kind 1000TPA facility to recover monomers from spent textiles via a proprietary chemical recycling process, including scale-up from an existing lab-scale processes.
Pre-FEL study and FEL1 design of a primarily greenfield 150TPD ag-based pulp molded fiber facility, including feedstock handling and separation, material storage, semi-chem pulping, stock preparation, and molding.
Front end engineering study to evaluate the feasibility of firing a secondary biomass fuel in three separate biomass boilers at an existing facility in an effort to reduce the consumption of the primary fuel source.
Detailed design and structural dynamics engineering evaluation to analyze a 4000-hp existing power plant ID fan for an unbalance issue at an existing facility.
Red Flags Analysis report in support of client’s potential investment in a polystyrene recycling company and the planned scale up of their demonstration-level facility to a commercial scale.
Capital cost estimating and detailed design engineering for a $5MM TIC project to upgrade dry end handling capabilities at an existing chemicals facility.