This effort included detailed engineering on a four project Anaerobic Digestion to biogas program with site locations in Georgia and California. The facilities were located on existing dairy farms of approximately 12,000 cows each...
Existing mill conversion from fine paper to linerboard production using 100% OCC furnish including new OCC facility and warehouse, conversion of existing machine, conversion of two boilers, and other utility upgrades.
This effort included the completion of the conceptual design (FEL2) phase for a $5 million USD water sustainability program for an existing Fiber Optics facility with a goal to reduce water consumption at the site by 80%.
Preliminary engineering in support of a developer commercializing a first-of-a-kind process to capture and store CO2 via natural water sources adjacent to industrial point source emitters.
Detailed design, procurement, and construction for a $100 million fly ash, bottom ash, and pyrites handling and transport conversion EPC project to meet Coal Combustion Residuals (CCR) environmental regulations.
FEL1 engineering design for a novel critical elements recovery facility funded by ARPA-e to process 1 ktpd of ultramafic tailings, integrating direct air capture of CO2 for carbon sequestration and electrolytic production of sulfuric acid.
Project management and construction oversight for an $8 million chemical manufacturing facility upgrade, including direct supervision of detailed design and construction bid process.
FEL1 Engineering and Site Selection services for a 200,000 TPY, First-of-its-Kind, Commercial Scale Facility to manufacture Ultra-low-Carbon Cement, co-located at an existing cement plant.
Front-end engineering and project development services to determine feasibility and conceptual layout for 400 MW-DC solar facility with 200-MW BESS located in Nebraska.
FEL2 Engineering and Owner’s Engineering Services for a 280 TPD Tissue Machine Process Air System Replacement project as part of a Fleet-wide Rebuild Program.